Scheduled Maintenance - North Carolina Colocation PDUs
Scheduled Maintenance Report for Smartt
Completed
The scheduled maintenance has been completed.
Posted Sep 11, 2021 - 15:00 PDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 11, 2021 - 10:00 PDT
Scheduled
We will replace the PDUs used by co-location clients in RDU with eight port smart PDUs. This will require bringing the existing power circuits offline.

Equipment with redundant PSUs will not experience downtime. Equipment with single PSUs still connected to the power circuits will be offline during the replacement time.
Posted Sep 10, 2021 - 15:53 PDT
This scheduled maintenance affected: VPS & VPC (RDU Virtual Cluster).